 Current Factory/Workshop Work Load as at:  

Current Major Projects/Installations

 

Project 103967 - New Plymouth - 01/01/2018 >> 01/02/2018 - Lift Rope & Sheave Repair

Project 103971 - Christchurch - 08/11/2017 >> 15/11/2017 - New New Dumb Waiter Installationn - Confirmation Expired

Project 103980- New Plymouth - 01/01/2018 >> 30/01/2018- New Lift Passenger Installation - Confirmed

Project 103981 - New Plymouth - 01/01/2018 >> 30/04/2018- New Lift Passenger Installation - Confirmed

Project 103968- New Plymouth - 01/01/2018 >> 19/02/2018- Goods Lift Upgrade - Confirmed

 

Current Minor Projects/Installations

Domestic Dumb Waiter install teams - current work load (20% Factory time remaining) 01/02/2018 to 30/06/2018

Workshop work load - variable up to 30/06/2018

Lift Manufacturing Factory

Lead Time for Drawings - 2 weeks
Lead Time for Manufacture - 7 weeks (from drawings)
Lead Time for Shipping - up to 6 Weeks (from manufacturing)

 

New clients looking at our products are advised the shipping and/or install dates
are now into mid 2018 before we can supply.
However we will supply quotations and accept orders for work from 01/02/2018 for the year 2018

PLEASE NOTE
All pending projects may roll up to an earlier date if waiting a client confirmation not made by window expiry date - any project confirmation missing expiry date will be subject to re-booking workshop time at a later date.
 
  